M
Mark Durrenberger
Hi all,
Oak Associates now offers an add-in for MS Project 2002-2003 that allows you
to range estimate activity effort and duration. The tool also runs a Monte
Carlo analysis using your range duration estimates. The Monte Carlo
simulation is an inexpensive alternative to other risk analysis tools.
The tool is called Ranger and it is available for a 30-day free trial. You
can learn more about it at:
http://www.oakinc.com/ranger
Thanks for checking it out,
Mark
--
_________________________________________________________
Mark Durrenberger, PMP
Principal, Oak Associates, Inc, www.oakinc.com
"Advancing the Theory and Practice of Project Management"
________________________________________________________
The nicest thing about NOT planning is that failure
comes as a complete surprise and is not preceded by
a period of worry and depression.
- Sir John Harvey-Jones
Oak Associates now offers an add-in for MS Project 2002-2003 that allows you
to range estimate activity effort and duration. The tool also runs a Monte
Carlo analysis using your range duration estimates. The Monte Carlo
simulation is an inexpensive alternative to other risk analysis tools.
The tool is called Ranger and it is available for a 30-day free trial. You
can learn more about it at:
http://www.oakinc.com/ranger
Thanks for checking it out,
Mark
--
_________________________________________________________
Mark Durrenberger, PMP
Principal, Oak Associates, Inc, www.oakinc.com
"Advancing the Theory and Practice of Project Management"
________________________________________________________
The nicest thing about NOT planning is that failure
comes as a complete surprise and is not preceded by
a period of worry and depression.
- Sir John Harvey-Jones