D
Dr. Wolfgang Hintze
How can I do valid risk analyses within Project?
The built-in procedure PERT is only of limited value. Here to each
activity there are assined three durations, optimistic, realistic, and
pessimistic. It is then possible to display three planning scenarios
(optimistic, realistic, pessimistic). But the drawback is that for each
scenario the same type of duration is taken for *all* activities, i.e.
if I choose the optimistic scenario for all activites in the plan the
optimistic duration is taken. (On the other hand it is helpful to be
able to display the average plan scenario.)
What I would like to see is the effect of a certain mixture of the types
of activity types. Hence my question: is there a Monte-Carlo simulation
framework within, or attached to, MS-Project, similar to the MS-Excel
framework called "CrystalBall"?
Thanks in advance for any hints.
Best regards,
Wolfgang
The built-in procedure PERT is only of limited value. Here to each
activity there are assined three durations, optimistic, realistic, and
pessimistic. It is then possible to display three planning scenarios
(optimistic, realistic, pessimistic). But the drawback is that for each
scenario the same type of duration is taken for *all* activities, i.e.
if I choose the optimistic scenario for all activites in the plan the
optimistic duration is taken. (On the other hand it is helpful to be
able to display the average plan scenario.)
What I would like to see is the effect of a certain mixture of the types
of activity types. Hence my question: is there a Monte-Carlo simulation
framework within, or attached to, MS-Project, similar to the MS-Excel
framework called "CrystalBall"?
Thanks in advance for any hints.
Best regards,
Wolfgang