G
Gil
Hi,
Would you help me with the following?
Let's say a resource standard rate is 1000$/month (a fixed sum
paycheck at the end of every calendar month), and this is what I input
in the resource sheet.
If I assign this resource to work on a 180hrs task, at 150% units, the
duration of the task is 15days, less than a month, but the cost
Project calculates for the task is 1125$.
I guess this is because 1000/160=6.25$/hour, and 6.25*180=1,125
But the resource is still getting payed 1000$ for the whole month,
even if he or she are working more than 160 hours per months.
Can project calculate the real cost for this scenario?
Thanks,
Gil
Would you help me with the following?
Let's say a resource standard rate is 1000$/month (a fixed sum
paycheck at the end of every calendar month), and this is what I input
in the resource sheet.
If I assign this resource to work on a 180hrs task, at 150% units, the
duration of the task is 15days, less than a month, but the cost
Project calculates for the task is 1125$.
I guess this is because 1000/160=6.25$/hour, and 6.25*180=1,125
But the resource is still getting payed 1000$ for the whole month,
even if he or she are working more than 160 hours per months.
Can project calculate the real cost for this scenario?
Thanks,
Gil