S
SW
Is anyone running with the Timesheet set to "Weekly" time unit and
experiencing issues? For example, in a Fixed Unit task of 1d/8hrs the
Resource enters 20hrs in their Timesheet. When approved, the task in MSP is
now 1d/20hrs - I was expecting to see 2.5d/20hrs which is what I would get if
I manually updated the task.
Also, Administrative time can only be entered by using the "Plan
Administrative Time" command.
I'd be very interested in hearing other experiences.
experiencing issues? For example, in a Fixed Unit task of 1d/8hrs the
Resource enters 20hrs in their Timesheet. When approved, the task in MSP is
now 1d/20hrs - I was expecting to see 2.5d/20hrs which is what I would get if
I manually updated the task.
Also, Administrative time can only be entered by using the "Plan
Administrative Time" command.
I'd be very interested in hearing other experiences.