MOPS 2007 - issue with Timesheet set to Weekly time unit?

S

SW

Is anyone running with the Timesheet set to "Weekly" time unit and
experiencing issues? For example, in a Fixed Unit task of 1d/8hrs the
Resource enters 20hrs in their Timesheet. When approved, the task in MSP is
now 1d/20hrs - I was expecting to see 2.5d/20hrs which is what I would get if
I manually updated the task.
Also, Administrative time can only be entered by using the "Plan
Administrative Time" command.
I'd be very interested in hearing other experiences.
 