Thanks for the advice folks - I have checked out the calendars as recommended
by Julie and they all agree. I took the opportunity to take a closer look at
hours in the various veiws available. The problem was reported by a user who
had seen it on his task view sheet in Web access, in Project pro his time
shows up as 1 day but I have now taken a look at the time in hours in the
Resource Useage view - it is correct, ie not 8 hours. Similarly a quick
analysis of the project using the OLAP cube shows the correct time - so it is
only wrong in the resource task sheet in PWA. Very odd.
by Julie and they all agree. I took the opportunity to take a closer look at
hours in the various veiws available. The problem was reported by a user who
had seen it on his task view sheet in Web access, in Project pro his time
shows up as 1 day but I have now taken a look at the time in hours in the
Resource Useage view - it is correct, ie not 8 hours. Similarly a quick
analysis of the project using the OLAP cube shows the correct time - so it is
only wrong in the resource task sheet in PWA. Very odd.