More than 5 shift entries per day?

D

Dale Newman

I have a resource that has 3 shifts daily. Each shift has a lunch. One
shift starts on the previous day (e.g. 11 PM previous day TO 7 AM day of). I
think I would need these shift entries for my calendar:

1. 12 AM to 4 AM - 3rd Shift Before Lunch
2. 4:30 AM to 7 AM - 3rd Shift After Lunch
3. 7 AM to 12 PM - 1st Shift Before Lunch
4. 12:30 PM to 3 PM - 1st Shift After Lunch
5. 3 PM to 8 PM - 2nd Shift Before Lunch
6. 8:30 PM to 11 PM - 2nd Shift After Lunch
7. 11:pM to 12 AM - 3rd Shift Before Lunch - Actually Part Next Day

Well, there are only 5 shift entries. Is this a limitation that can not be
overcome? I would expect more than one person in the world would want to
have 3 shifts, and consider lunches as non-working time.
 
J

Jan De Messemaeker

Hi Dale,

Will any resource ever work following this working time plan?
When you are going to apply it thatis what will happen.
The resource will be scheduled for all 3 shifts and work 22,5 hours per day.
I don't think this is what you need; if not you may well be the only person
in the world :)

Hope this helps,
 
G

Gérard Ducouret

Hello Dale,



As Jan explained, 22,5 hours per day is a little too much for most of human
beings.

I guess that you have 3 shifts per day (3 teams). So you would have to
create 3 calendars and assign these different calendars to the appropriate
resources.
Tools / Change Working Time... / New...

Gérard Ducouret
 
D

Dale Newman

Thank you for your replies.

Perhaps I'm using this wrong. But, the resource I intend to apply a 3 shift
calendar to is not a human being. It is a "work-center" operated by three
shifts of people.

Creating 3 calendars would be fine, if, I could assign 3 calendars to the
same resource. Yet, I can only assign one calendar to each resource as it's
"base" calendar. So, making 3 calendars wouldn't help.

I guess I assumed I wouldn't be the only person in the whole world to need
this, because I'm thinking of a single work-center, that is run 24-7 by three
teams / shifts. But, most people don't try to "level-load" a work-center in
a manufacturing environment using MS Project either...

Thanks for you help. If I'm stuck with 5 shift entries only, and there's no
way for me to work around it, I'll just have to trim out the lunches and
account for the missing half-hour elsewhere.

Thanks again,

Dale
 
J

Jan De Messemaeker

Hi,

I owe you an apology.
I simply ASSUMED you were wrong, and that is not good (to say it softly)
Sorry!!
 
G

Gérard Ducouret

Hi Dale,

What I did in a practical case which seems close to your :
I divided the resource "work center" in 3 resources. Each of them with a
specific calendar :

- Work Center Day Shift 06:00 - 14:00
- Work Center Swing Shift 14:00 - 22:00
- Work Center Graveyard Shift 22:00 - 06:00

Gérard Ducouret
 
D

Dale Newman

Gérard,

Thanks for the advice. Splitting up the Resource into Resource Shift
combinations may give me the detail I'd like to have :)

Thanks,

Dale
 

Ask a Question

Want to reply to this thread or ask your own question?

You'll need to choose a username for the site, which only take a couple of moments. After that, you can post your question and our members will help you out.

Ask a Question

Top