R
richardharwood
Hello,
BACKGROUND:
I currently use Microsoft Project to chart/display the forthcoming
operations of our company. We do not use Project for any CPA or other
uses - we simply print out the months chart to use as a production
schedule.
Each row contains the name of a workshop operative. Each column
represents a different day of the week sequentially. Blocks are shown
to represent which jobs each employee will be working on at any given
point.
THE PROBLEM:
Occasionally we have to shuffle or ammend the production schedule,
typically once a week. For example;
John Smith is scheduled to be working on Project A for July
1st,2nd,3rd,4th and 5th. However, Project B has been brought forward
and therefore John will now work on Project A for 1st, 2nd and 3rd
July, but will work on Project B for 4th and 5th July.
Whenever I create a new project, or shorten an individual timespan, all
the blocks which follow (i.e. 6th July onwards) remain in their
original places. Ideally I want these to automatically shift left, so
that they again meet the shortened length of Project A. At the moment,
I have to do this manually and it does take some time...
Is there any way that blocks can be made to automatically move left
where possible, rather than staying at their original dates?
Any help on this matter would be much appreciated.
Thank You.
Richard
BACKGROUND:
I currently use Microsoft Project to chart/display the forthcoming
operations of our company. We do not use Project for any CPA or other
uses - we simply print out the months chart to use as a production
schedule.
Each row contains the name of a workshop operative. Each column
represents a different day of the week sequentially. Blocks are shown
to represent which jobs each employee will be working on at any given
point.
THE PROBLEM:
Occasionally we have to shuffle or ammend the production schedule,
typically once a week. For example;
John Smith is scheduled to be working on Project A for July
1st,2nd,3rd,4th and 5th. However, Project B has been brought forward
and therefore John will now work on Project A for 1st, 2nd and 3rd
July, but will work on Project B for 4th and 5th July.
Whenever I create a new project, or shorten an individual timespan, all
the blocks which follow (i.e. 6th July onwards) remain in their
original places. Ideally I want these to automatically shift left, so
that they again meet the shortened length of Project A. At the moment,
I have to do this manually and it does take some time...
Is there any way that blocks can be made to automatically move left
where possible, rather than staying at their original dates?
Any help on this matter would be much appreciated.
Thank You.
Richard