During regular updates of our project plan
- tasks that were originally scheduled before the status date and have
started, have the remaining parts of the task moved after the status date.
- but tasks originally scheduled before the status date and have NOT
started, remain scheduled before the status date (so essentially these tasks
are scheduled in the past).
How do we have the tasks originally scheduled before the status date and
have NOT started moved to after the status?
- tasks that were originally scheduled before the status date and have
started, have the remaining parts of the task moved after the status date.
- but tasks originally scheduled before the status date and have NOT
started, remain scheduled before the status date (so essentially these tasks
are scheduled in the past).
How do we have the tasks originally scheduled before the status date and
have NOT started moved to after the status?