move tasks from old project to new project with resource and actuals

M

Micheal

Hi,

I want to close my current project and make new project and want to move the
few tasks from old project to new project with actuals .
any idea or method to resolve this issue.

Regards
Micheal
 
D

Dale Howard [MVP]

Micheal --

Because of the risks associated with copying/cutting and pasting tasks in
enterprise projects, if it were my project, I would create the new project
and then manually enter the actuals to match those entered in the old
project. Just a thought. Perhaps the others have an opinion, too.
 
J

Jan M.

Hi Micheal,

maybe you could save your project as an MPP file, save it using the "Import
project to the enterprise" wizard and delete what you don't need.

Jan M.
 