I am trying to plan a project in MSP 2003 and I want all tasks to revolve
around a milestone.
This milestone has predessors and sucsessors. I want to drag the milestone
to the left and right and have all connected tasks move with it keeping the
same number of days between the tasks both in front and behind.
i.e. the milestone has a task that has to happen 2 weeks before and some
that have to happen 6 weeks. Also there are tasks that have to happen 3 weeks
after etc etc.
I have around 30 predessors and 25 sucsessors, i.e. a lot of dependances.
What is the easiest way to do this?
Many thanks for the help
Ben
around a milestone.
This milestone has predessors and sucsessors. I want to drag the milestone
to the left and right and have all connected tasks move with it keeping the
same number of days between the tasks both in front and behind.
i.e. the milestone has a task that has to happen 2 weeks before and some
that have to happen 6 weeks. Also there are tasks that have to happen 3 weeks
after etc etc.
I have around 30 predessors and 25 sucsessors, i.e. a lot of dependances.
What is the easiest way to do this?
Many thanks for the help
Ben