R
rajanmisra
Hi
We are using Project Server 2003 with Service Pack 1.
We use "Managed Time Period".
I noticed that ,in case for a task a resource has reported some Actual
Work on Dec 15 with the assignment start date as Dec 15 .And after that
if we change the start date of the task to Nov 29 then it moves the
Actual Work from Dec 15 to Nov 29.
It does make some sense to me , coz basically if actual work was not
done than the assignment has not started by then. I hope I am making
sense here.
But I want to come up with a more concrete explanation for my users,
for this behaviour.
We don't use any baselines. Could this be a potential problem.
Thanks a lot in advance !!!
Rajan
We are using Project Server 2003 with Service Pack 1.
We use "Managed Time Period".
I noticed that ,in case for a task a resource has reported some Actual
Work on Dec 15 with the assignment start date as Dec 15 .And after that
if we change the start date of the task to Nov 29 then it moves the
Actual Work from Dec 15 to Nov 29.
It does make some sense to me , coz basically if actual work was not
done than the assignment has not started by then. I hope I am making
sense here.
But I want to come up with a more concrete explanation for my users,
for this behaviour.
We don't use any baselines. Could this be a potential problem.
Thanks a lot in advance !!!
Rajan