KD said:
In project, if I have two tasks and the first one is 100% complete, and the
second one needs to be moved out from the start date set up by the link, how
can I move it without deleting the link or entering a hard constraint?
Logic tells me I should enter in a task which shows the reason for the
delay, however this does not always seem approprioate in every schedule for
every circumstance.
Am I missing the logic here?
Thank you
KD,
No, you're not missing any logic. The only reason links are added
between tasks is to emulate a true dependency. For example, task B
cannot start until task A finishes (e.g. the prototype can't be built
until the design is complete, or the taping and finishing can't be
applied until the sheetrock is up). However for various reasons although
task B may be dependent on task A, task B may not start immediately.
Maybe there is a delay waiting for parts to arrive, or maybe its a
funding availability issue, or any number of other things. If the delay
is known it can be included the link. For example, if task B can't start
until 5 working days after task A completes, then the predecessor for
task B might be: FS+5d. If another specific task is the reason for the
delay (e.g. task A finished but an approval cycle is required before
task B can start), then that delaying task should be included in the
plan as an additional task.
Every plan requires careful thought to develop. Every task must have a
successor, even if its just the final completion milestone. If tasks
should be logically linked then link them, but don't link tasks just for
the sake of having a continuous flow of logic. But remember, plans are
always dynamic. The plan you start with will most certainly need to be
modified as it unfolds in the real world. That includes reviewing all
the schedule logic and making adjustments as necessary.
Hope this helps.
John
Project MVP