H
hinrgsunshine2
Project Server 2003
Managed Time Periods, with resources entering actual work each week
We run a query out of the Portfolio Analyzer that shows how much
"remaining work" a resource has (work - acutal work) on
a specific project. This is done for each quarter to show what didn't get
done
or was overplanned. The project manager needs to then review this and
decide to either purge the work that wasn't done or move it forward into the
current/future quarters.
Let's say a resource shows that he has the following planned work, on 1
task, that spans several quarters:
100 hours in Q1
100 hours in Q2
100 hours in Q3
In Q1 he only does 50 hours. It's now Q2. That 50 hours that didn't get
done and needs to either move into Q2 or get purged.
If the project manager decides to purge the remaining work we
been using the task usage view in MS Project Pro 2003
to compare Actual Work Protected to Work. Where there is a variance in the
past
we edit the work to match the actual work... essentially purging work that
wasn't performed. We republish and we're done. What we're seeing happen
is that when we do this, then we sync to actuals, the work comes back and no
longer matches actual work protected.
There's GOT to be an easier way for us to get rid of the
overplanned/un-performed work in the past.
Managed Time Periods, with resources entering actual work each week
We run a query out of the Portfolio Analyzer that shows how much
"remaining work" a resource has (work - acutal work) on
a specific project. This is done for each quarter to show what didn't get
done
or was overplanned. The project manager needs to then review this and
decide to either purge the work that wasn't done or move it forward into the
current/future quarters.
Let's say a resource shows that he has the following planned work, on 1
task, that spans several quarters:
100 hours in Q1
100 hours in Q2
100 hours in Q3
In Q1 he only does 50 hours. It's now Q2. That 50 hours that didn't get
done and needs to either move into Q2 or get purged.
If the project manager decides to purge the remaining work we
been using the task usage view in MS Project Pro 2003
to compare Actual Work Protected to Work. Where there is a variance in the
past
we edit the work to match the actual work... essentially purging work that
wasn't performed. We republish and we're done. What we're seeing happen
is that when we do this, then we sync to actuals, the work comes back and no
longer matches actual work protected.
There's GOT to be an easier way for us to get rid of the
overplanned/un-performed work in the past.