M
MSPLearner
I have about 20 schedules (separate .mpp files) that were created and saved
in a Test Instance of Project Server 2007. I need to move all 20 to a
Production Instance of PRoject Server 2007. This schedule set consists of one
"Master Give/Get" schedule that ties external dependencies between the
remaining schedules. So the 19 schedules have external dependancies ONLY to
"Master Give/Get".
I want to avoid breaking and having to redo the external links. What is my
approach (sequence) to loading the schedules so that if possible, I don't
break the links? Or is there an import/export facility that might be useful
for this task?
Thanks in advance
in a Test Instance of Project Server 2007. I need to move all 20 to a
Production Instance of PRoject Server 2007. This schedule set consists of one
"Master Give/Get" schedule that ties external dependencies between the
remaining schedules. So the 19 schedules have external dependancies ONLY to
"Master Give/Get".
I want to avoid breaking and having to redo the external links. What is my
approach (sequence) to loading the schedules so that if possible, I don't
break the links? Or is there an import/export facility that might be useful
for this task?
Thanks in advance