K
Kerry
I have a PM that is starting a plan, her first plan. Whenever she attempts
to add a task it's fine until she adds a resource. Then it changes the start
date to 12/31/2012. I can open her plan and create a task, and assign
a resource and the start stays at 7/29/2009. When I view it, the entire plan
looks
fine. It ends in 2009. When she opens it, it ends in 2013. Any suggestions?
I'm stumped.
to add a task it's fine until she adds a resource. Then it changes the start
date to 12/31/2012. I can open her plan and create a task, and assign
a resource and the start stays at 7/29/2009. When I view it, the entire plan
looks
fine. It ends in 2009. When she opens it, it ends in 2013. Any suggestions?
I'm stumped.