D
danimalx
Hi all,
After creating my initial WBS and adding tasks and sub tasks, I've com
across the need to move tasks around - via cut/paste. In doing so thos
tasks I've moved around now get populated with Start No Earlier Tha
constraints and constraint date of N/A and I'm unable to move the bar
around in the Gantt Chart due to the date constraints. If I try to se
it back manually, then move the bar again it resets back to the SNET an
N/A settings.
My question is, how then should I move tasks around and still preserv
the As Soon as Possible and N/A Constraint date settings so I don't hav
these problems? Or am I off track with my cause/effect reasoning of wha
is going on here?
Thanks in advance for any insight
After creating my initial WBS and adding tasks and sub tasks, I've com
across the need to move tasks around - via cut/paste. In doing so thos
tasks I've moved around now get populated with Start No Earlier Tha
constraints and constraint date of N/A and I'm unable to move the bar
around in the Gantt Chart due to the date constraints. If I try to se
it back manually, then move the bar again it resets back to the SNET an
N/A settings.
My question is, how then should I move tasks around and still preserv
the As Soon as Possible and N/A Constraint date settings so I don't hav
these problems? Or am I off track with my cause/effect reasoning of wha
is going on here?
Thanks in advance for any insight