Moving tasks to status date

D

Dale N

Even though under Project/Options/Calculation I have selected “move end of
completed parts back to status date†and “move start of remaining parts
forward to status dateâ€, the activities are not moved to the status date. Why
is this?
 
C

Catfish Hunter

Dale, are you calculating the project?
1) Project>Project Information>Status Date________________.
2)Tools>Tracking>Update Project>Reschedule Uncompleted Work to Start
After___________________.
 
G

Gérard Ducouret

Hello,
These options are not triggered after the event. They are triggered when you
enter a new tracking data on the task.
 
D

Dale N

Thanks guys!! Appreciate the help!

Gérard Ducouret said:
Hello,
These options are not triggered after the event. They are triggered when you
enter a new tracking data on the task.
 