moving tasks

D

DaveB

Hi

I've made a Gant chart and would like to move all tasks 1 week... is there a facility to do this

Also, is there a way to allocate percentages of time to tasks, enter the amount of time available and have the individual task times calculated

Thanks

Dave
 
J

Jan De Messemaeker

Hi Dave,

As long as you haven't introduced actual work:
Tools, Customize, Toolbars, show the analysis toolbar
Click Adjust Dates
Shift the project start by the time needed.
HTH


--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/index.htm
32-495-300 620
DaveB said:
Hi,

I've made a Gant chart and would like to move all tasks 1 week... is there a facility to do this?

Also, is there a way to allocate percentages of time to tasks, enter the
amount of time available and have the individual task times calculated?
 
J

Jan De Messemaeker

Hi again,

Regarding your second question can you be more precise as to what you want
to enter when?
The rare two "times", Duration and Work (tied by teh percenbtage of their
tiome (a) reesource(s) are planned to work on it).
This being said, what exactly do you want?

Greetsings,

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
http://users.online.be/prom-ade/index.htm
32-495-300 620
DaveB said:
Hi,

I've made a Gant chart and would like to move all tasks 1 week... is there a facility to do this?

Also, is there a way to allocate percentages of time to tasks, enter the
amount of time available and have the individual task times calculated?
 