Logistics for Newday
I would like to change all saturdays and sundays between 25 Jul and 15 Aug 09
to working days. I have tried to do this on several occasions but the project
reverts to making those dates nonworking even when I have made them
'exception days'. Please could you tell me where I am going wrong; I follow
this method:
Tools, Change Working Time, scroll bar to 25 Jul, select details, sselect
working times (0800 - 1200/1300 - 1700),select recurrence pattern 'daily',
select range of recurrence 25 Jul to 15 Aug 09, select ok.
Thank you!