MP 07, Working Days

  • Thread starter Logistics for Newday
  • Start date
L

Logistics for Newday

I would like to change all saturdays and sundays between 25 Jul and 15 Aug 09
to working days. I have tried to do this on several occasions but the project
reverts to making those dates nonworking even when I have made them
'exception days'. Please could you tell me where I am going wrong; I follow
this method:
Tools, Change Working Time, scroll bar to 25 Jul, select details, sselect
working times (0800 - 1200/1300 - 1700),select recurrence pattern 'daily',
select range of recurrence 25 Jul to 15 Aug 09, select ok.

Thank you!
 
M

Mike Glen

Hi ,

Welcome to this Microsoft Project newsgroup :)

I don't have an answer for you. I tried what you did step by step and
Project keeps the changes even when closing down Project and re-opening it.
When you re-open your project, are you saying that the details have
disappeared from the Change Working Time dialog?

FAQs, companion products and other useful Project information can be seen at
this web address: http://project.mvps.org/faqs.htm

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
See http://tinyurl.com/2xbhc for my free Project Tutorials
 