Hello All,
I need to send the project schedule to the Client but it should not
have resources and cost information.
So, I decided to export the schedule using the "task" map and import it
again to a new project file using the same map.
The problem is that some tasks datas (duration, work, % completed,
start and finish dates) in the imported schedule are different from the
original schedule.
Do you know why is it happening? How can I fix it? Or even, is this the
most adequate procedure for the situation?
Regards,
Luis Felipe S. Monteiro
I need to send the project schedule to the Client but it should not
have resources and cost information.
So, I decided to export the schedule using the "task" map and import it
again to a new project file using the same map.
The problem is that some tasks datas (duration, work, % completed,
start and finish dates) in the imported schedule are different from the
original schedule.
Do you know why is it happening? How can I fix it? Or even, is this the
most adequate procedure for the situation?
Regards,
Luis Felipe S. Monteiro