Hi,
We have implemented project server in our organization.
When i baseline a plan in MPP & published and the resources have updated the
actual for some task through project web access, after that i found that i
missed some task in planning. So i inserted the new task in between the plan
which has no predecessors and baseline the MPP & published and updated actual
for the task planned. The problem is when i inserted the task the remaining
plan has been changed which i haven’t noticed it and have updated the actual
works, now my schedule variations shows that i am not in control but in
actual i am in control.
Please help me how to resolve this issues and show that schedule is under
control in MPP
Thanks & Regards,
Ramesh
We have implemented project server in our organization.
When i baseline a plan in MPP & published and the resources have updated the
actual for some task through project web access, after that i found that i
missed some task in planning. So i inserted the new task in between the plan
which has no predecessors and baseline the MPP & published and updated actual
for the task planned. The problem is when i inserted the task the remaining
plan has been changed which i haven’t noticed it and have updated the actual
works, now my schedule variations shows that i am not in control but in
actual i am in control.
Please help me how to resolve this issues and show that schedule is under
control in MPP
Thanks & Regards,
Ramesh