MPS2007, how to set week start day in Data Analysis views (OLAP)

  • Thread starter Vadim Gerya, PMP
  • Start date
V

Vadim Gerya, PMP

Hi ALL !

MSP2007 generates time dimention in OLAP cubes. By default WEEK starts at
Sunday. It is important for us to see "Monday-Sunday" weeks in Data Analysys
Views.
Does anyboby know how to change WEEK start to Monday?

Thanks in advance ..
 
N

NZ Projects

I "think" (do not have it front of me to check), it's in the timesheet
settings in PWA.
 
M

Matteo

You have to go from PWA to Server Settings --> Time and Task Management -->
Task Settings and Display

Hope this help you.

Matteo
 