MS Proj 2003 Date Function

C

Choopster

Looking to compare 2 date columns (start date vs baseline date). I'd like to
be able to have 2 colums -
1. showing difference in days
2. showing a grafical indicator (+ or -)

Anyone know how?

Much appreciated
 
J

Jan De Messemaeker

Hi,

1. Customize a duration field with the function ProjDateDiff
2. (one of several possibilities) customize a second duration dfield with as
formula equal o the first one and set the graphical indicators for less than
0;, equals zero, greater than 0.

HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 