MS PROJ 98 CALENDAR QUERY

A

AC

Hi, I have customised my calendar to the following setting
using the Option selection:

Default Start Time: 9:00AM
Default End Time: 6:30PM
Hours per day: 8.5
Hours per week:42.5

Then I set the above setting to default.

Problem (as perceived by me):
When I goes to Change Work Time, the default time is still
set as

From: 8:00AM to 12:00PM
From: 1:00PM to 5:00PM

which is not what I want :<

So, I then go and highlight all the working days for all
the months that the project will work through and change
the default working time manually.

Can someone advise if I have done something wrongly such
that the customised timing is not reflecting in the Change
Work Time section.

Thanks!!
 
S

Sarah

No, you did not do anything wrong. The two working time settings are
not connected in MS Project. You must change the working time on the
Options>Calendar tab and on the Change Working Time>Standard calendar
in order for it to truly affect your project. If you have matching
start and end times in both places, you're good to go.

Sarah
 
A

AC

Hi Sarah and Mike, thanks for the advice.

I get it now!!!!

PS: I dont have to highlight month by month to change the
work time, just highlight Mon to Fri and it will do the
change for all the years in the calendar :>

MVPS, great site!!
 
M

Mike Glen

You're welcome, AC :)

Mike Glen
MS Project MVP

AC said:
Hi Sarah and Mike, thanks for the advice.

I get it now!!!!

PS: I dont have to highlight month by month to change the
work time, just highlight Mon to Fri and it will do the
change for all the years in the calendar :>

MVPS, great site!!
 