Hi, I have customised my calendar to the following setting
using the Option selection:
Default Start Time: 9:00AM
Default End Time: 6:30PM
Hours per day: 8.5
Hours per week:42.5
Then I set the above setting to default.
Problem (as perceived by me):
When I goes to Change Work Time, the default time is still
set as
From: 8:00AM to 12:00PM
From: 1:00PM to 5:00PM
which is not what I want :<
So, I then go and highlight all the working days for all
the months that the project will work through and change
the default working time manually.
Can someone advise if I have done something wrongly such
that the customised timing is not reflecting in the Change
Work Time section.
Thanks!!
using the Option selection:
Default Start Time: 9:00AM
Default End Time: 6:30PM
Hours per day: 8.5
Hours per week:42.5
Then I set the above setting to default.
Problem (as perceived by me):
When I goes to Change Work Time, the default time is still
set as
From: 8:00AM to 12:00PM
From: 1:00PM to 5:00PM
which is not what I want :<
So, I then go and highlight all the working days for all
the months that the project will work through and change
the default working time manually.
Can someone advise if I have done something wrongly such
that the customised timing is not reflecting in the Change
Work Time section.
Thanks!!