P
Paul
1. Is there a way to drag only the left edges of a bar without moving
the right edge?
2. If I have several bars for which I have to change the start date to
a common date without changing their end dates (which are not common),
it doesn't seem to work by just selecting the WBS tasks and pulling up
the task information window. Setting the start date this way causes
their end dates to change so as to maintain the same duration. Is
there a way to set a common start date without changing the end dates?
the right edge?
2. If I have several bars for which I have to change the start date to
a common date without changing their end dates (which are not common),
it doesn't seem to work by just selecting the WBS tasks and pulling up
the task information window. Setting the start date this way causes
their end dates to change so as to maintain the same duration. Is
there a way to set a common start date without changing the end dates?