MS-Project 2000

L

Larry

Want to print with Gant project starting June, but
printout includes 2-weeks (May) prior to start. How to
delete/not include those 2blanks weeks. No tasks are in
this 2 week period for May.
 
J

JackD

File menu / print / in the timescale section on the lower left set the start
date for the print.
Adjust as necessary until it shows what you want. It is not precise and may
take some trial and error.

-Jack
 