M
Manuel
Hi there! My team is currently evaluating MS Project 2003
Professional (Server). One of the challenge my folks are
facing is to be able to use the concept of WBS (Work
Breakdown Structure) in MS Project. Basically the
objective is to define the sub-components of system when
we design a new product so that we can build a history of
effort to develops these sub components.
Thsi was a "simple" task in Primavera. Can anybody help?
Thanks
Manuel
Professional (Server). One of the challenge my folks are
facing is to be able to use the concept of WBS (Work
Breakdown Structure) in MS Project. Basically the
objective is to define the sub-components of system when
we design a new product so that we can build a history of
effort to develops these sub components.
Thsi was a "simple" task in Primavera. Can anybody help?
Thanks
Manuel