MS Project 2002 - EVM Table

R

Ravi

Hi,

I'm new to the newsgroup.

I was using MS Proj 2002 today and created a new project,
baselined it and viewed the Earned Value Table under the
Tracking Gantt.

This is what I found:

1. If all the tasks have been sequenced before baselining,
after baslining the BCWP for each task is zero.

2. If no task has been sequenced when baselining, the BCWP
has a value based on the resource rate and duration but
the moment you sequence it after that, the BCWP reverts to
zero for the "sequenced" tasks; non-sequenced tasks
continue to hold the BCWP value.

3. If I use a project file created under Project 98 and
converted to 2002, everything is fine. When I converted
it to MS Project 2000, my BCWP values were reverted to
zero.

Has anyone encountered this before? If you did, did you
manage to fix it? How?

Regards,
Ravi
 
G

Gérard DUCOURET

Hi Ravi,
The BCWP is calculated on the basis of the Status date (Project / Project information)
Where is your Satus date (between the project's start and finish date ?)

Gérard Ducouret
 
R

Ravi

Hi Gerard,

My mistake. It is not BCWP but BCWS. The Planned value
must have a value based on the resource rates or any other
planned costs, but it shows zero.

Regards,
Ravi
-----Original Message-----
Hi Ravi,
The BCWP is calculated on the basis of the Status date
(Project / Project information)
 