D
Dasani
Completed:
- added all of the tasks
- added all dates/durations (included dependencies to some existing
release dates)
-added resources
-assigned percentage of availability for each resource on each task
- assigned overall percentage complete for each task
Where I need help:
- adding the actual work and ETCs without messing up everything else
(dates, duration, original work estimate)
Any advice?
- added all of the tasks
- added all dates/durations (included dependencies to some existing
release dates)
-added resources
-assigned percentage of availability for each resource on each task
- assigned overall percentage complete for each task
Where I need help:
- adding the actual work and ETCs without messing up everything else
(dates, duration, original work estimate)
Any advice?