Hi,
There is no direct way to this. When I say direct, I mean a way that is
supported by Microsoft. The PDS don't allow access to this feature. What
I did, is to write directly into the database, and it works like a
charm.
Since the update from "Hours" I was able to investigate further and created a
macro to allow the updating of resource non-working days. This is currently a
3 step process - Refresh my source data in Excel (coming from and SQL over
corp. directory), import this into Project as a task list, process the task
list with new macro to update each resources non-working time. This is more
than effective and will save many hours of manual loading of this data.
Issue Resolved - Thanks Sean Davies