I am using MS Project Professional 2003 and I have an issue, I am
assigning a task in my Project Schedule to Team member 'A' and when
publish this project then this same task is also showing in another
Team members 'B' Task list but I have not assign this task to Team
member 'B'. I don't know why in Team member 'B's Task list is showing
this Team member ‘A’s Tasks.
Please any one have idea why is happening, it will be very
appreciated..

Thanks,
Rahul
 
J

Jonathan Sofer

At any point, was Team Member B assigned to this task and published? If so,
then the assignment would show under Team Member B but with an X next to the
assignment representing that it has been deleted. Let me know if this was
possibly the case.

Jonathan
 