C
CraigM
I'm trying to use MS Project 2003 to create a high-level plan. I'm using 1
resource to represent a team which has a varying resource availability as
people get freed up from other projects.
As a simple example I have modelled my resource availality as:
April - 200%
May - 300%
June - December - 700%
and I have 3 tasks on which any number of resources can work. The tasks are:
1. 4 weeks
2. 8 weeks
3. 12 weeks
So I'd expect that during April, task #1 and #2 get worked on. Task #1
finishes at the end of April and #2 finishes at the end of May.
For task #3 I expect 2 people to work on it throughout May and all 7 people
to work on it from the start of June until it is finished.
However, when I level resources MS project just gives me a flat resource
profile meaning that the team are very underused through June.
How do I get MS project to make full use of the available resources?
- Craig
resource to represent a team which has a varying resource availability as
people get freed up from other projects.
As a simple example I have modelled my resource availality as:
April - 200%
May - 300%
June - December - 700%
and I have 3 tasks on which any number of resources can work. The tasks are:
1. 4 weeks
2. 8 weeks
3. 12 weeks
So I'd expect that during April, task #1 and #2 get worked on. Task #1
finishes at the end of April and #2 finishes at the end of May.
For task #3 I expect 2 people to work on it throughout May and all 7 people
to work on it from the start of June until it is finished.
However, when I level resources MS project just gives me a flat resource
profile meaning that the team are very underused through June.
How do I get MS project to make full use of the available resources?
- Craig