MS Project 2003 with task indent and duration

G

Gopal

Hi,

I am new to MS Project 2003, I would like to add the task with
Indent. I have created the Indent, but the duration is not getting
added when I add the duration for the sub tasks. why is it so? How to
update the task duration of the indent when i add in sub tasks?

Thanks in advance.

Thank you,
Gopal.
 
M

Manmeet Chaudhari

Hi Gopal

Indenting our outdenting the task will only change its level in the Project
schedule.
If you want duration of the sub task to add up to the duration of the
summary task then you will have to link the activites.

Use one of the available relationship and you will get the desired results.

To do so
Select the subtask now click on the Link Task icon available on the standard
toolbar.
 
D

Dale Howard [MVP]

Gopal --

The Duration of a summary task does not "add up" as you describe it. The
software calculates the Duration from the Start of the earliest subtask to
the Finish of the latest subtask. Hope this helps.
 
M

Mike Glen

Hi Gopal,

Welcome to this Microsoft Project newsgroup :)

You might like to have a look at my series on Microsoft Project in the
TechTrax ezine, particularly #2 on entering data, at this site:
http://tinyurl.com/2xbhc or this:
http://pubs.logicalexpressions.com/Pub0009/LPMFrame.asp?CMD=ArticleSearch&AUTH=23
(Perhaps you'd care to rate the article before leaving the site, :)
Thanks.)

FAQs, companion products and other useful Project information can be seen at
this web address: <http://www.mvps.org/project/>

Hope this helps - please let us know how you get on :)

Mike Glen
MS Project MVP
 