MS Project 2007 Child tasks keep moving...need help please.

D

dfresh

Currently having an issue with child task keep randomly moving from one
parent task to another. I spent 8 hours the other day fixing my project
plan to make sure all child task were under the correct parent tasks.
When I opened my project the next time, couple days later, some of the
child tasks had moved to other parent tasks. Has this happended to
anyone else or does anyone know how to correct this issue? Thank you.
 
J

Jim Aksel

Might you have a custom grouping applied?
Also, download and install the latest service packs. P2007 is currently on
SP1, plus a few other updates.

--
If this post was helpful, please consider rating it.

Jim Aksel, MVP

Check out my blog for more information:
http://www.msprojectblog.com
 