Kathy
I am updating a project plan in which the baseline hours were 16. I enter 4
for hours worked and then 5 for remaining. The next thing I know, MS Project
enters 2000 hours. I go back change the hours and then it adds 3000 to
another project.
I tried to call Microsost but unless I pay them - I cant talk with anyone.
Does anyone know why MS Project would just enter hours randomly into a task
(doesnt have to be the one I am working on)?
Thanks k
for hours worked and then 5 for remaining. The next thing I know, MS Project
enters 2000 hours. I go back change the hours and then it adds 3000 to
another project.
I tried to call Microsost but unless I pay them - I cant talk with anyone.
Does anyone know why MS Project would just enter hours randomly into a task
(doesnt have to be the one I am working on)?
Thanks k