MS Project 2007 not accepting constraints

M

mikejw

Can someone tell me what is going on when I change a constraint type and date
and the date remains the same? I've deleted the task and added back and it
still will not accept the new constraint date. Btw, I'm going from an SNE
date in Oct 08 to a Must Finish On date in Oct 2010.

Thanks.
 
J

Jan De Messemaeker

Hi,

Two possibilities:
- Either in Tools, Options, Calculation, calculation is set to manual
- Or, you have a circular relationship. Delete all dependencies from and to
summary tasks; that should rejuvenate your project.
HTH

--
Jan De Messemaeker
Microsoft Project Most Valuable Professional
+32 495 300 620
For availability check:
http://users.online.be/prom-ade/Calendar.pdf
 