M
mikejw
Hello,
I am developing a simple schedule with no resources but 2 tasks out of 100
are hazardous and I would like to make the schedule so that when these tasks
occur, no other tasks can occur. In other words, even though all tasks are
moving around as the schedule is being developed, I would like to make sure
no other tasks can be scheduled wherever these 2 hazardous tasks fall. These
2 tasks are serial to every other task in the schedule. Is there a way to do
this?
Thanks for your help.
Mike
I am developing a simple schedule with no resources but 2 tasks out of 100
are hazardous and I would like to make the schedule so that when these tasks
occur, no other tasks can occur. In other words, even though all tasks are
moving around as the schedule is being developed, I would like to make sure
no other tasks can be scheduled wherever these 2 hazardous tasks fall. These
2 tasks are serial to every other task in the schedule. Is there a way to do
this?
Thanks for your help.
Mike