The information you see in the resource usage view is assignment
information. The resource is scheduled on the assignment at the
start and finish dates. The Early Start, Early Finish, late
Start and Late Finish are task values and are not visible in the
resource usage view. It sounds as if the task early is equal to
the task start and the task early finish is equal to the task
finish.
You can view the Resource Allocation view (Resource Usage over
the Leveling Gantt) and add early start, late start, early
finish, late finish to the table. The Leveling Gantt also by
default shows slack graphically. Using the value in the slack
field, I suppose you could add assignment delay equal to the
total slack to force the assignment to equal the late start and
late finish. You'll need to add the assignment delay to the
Resource Usage view.
Julie
Project MVP