R
Rudolf
Hi,
I'm rather puzzled by the following situation:
in at least one project in project professional actual work entries are
shown in the Task-usage view that do not show in the pwa 2003 timesheet view
in that period of that resource. In the timesheet the tasks themselves are
shown but no work-entries.
It seems that this the case with some complete tasks but also with some
first day entries on tasks on which latter entries are shown correctly.
I would really appreciate your ideas as to what could have happened here.
But also, I am very interested in ways to locate as easily as possible each
occurence of this problem.
I'm rather puzzled by the following situation:
in at least one project in project professional actual work entries are
shown in the Task-usage view that do not show in the pwa 2003 timesheet view
in that period of that resource. In the timesheet the tasks themselves are
shown but no work-entries.
It seems that this the case with some complete tasks but also with some
first day entries on tasks on which latter entries are shown correctly.
I would really appreciate your ideas as to what could have happened here.
But also, I am very interested in ways to locate as easily as possible each
occurence of this problem.