Is there any way to prevent MS Project from automatically updating
Estimated Work when Actual Work is entered?
eg. Task has 1 day durtation and 0 hours or estimated work (scheduled
effort). When I update the actuals, it automatically updates the
estimated work to the same amount: entering 8 hours updates estimate
to 8 hours.
This is incorrect as prevents me from tracking project task overruns.
Does anyone know how to change that setting?