Ms Project adding new calendar ??

A

Aamir

Hi,

Any one know how to create "new" calendar in Ms Project 2003 wit
customized holidays/weekends, working hours etc

I tried under under "Tools > Change Working Time >> Create New Bas
Calendar" with everything of my own But the problems im facing are;

1. It creates for onyl 1 month that i change not for whole year
2. Even after i apply changes there is no change in project (eg.
changed holiday Sunday to Friday, but when i add task on sunday it say
its weekend)

What i want;

1. Customized calendar with Working Timing ( 0730AM - 1230PM & the
0100PM - 0415PM, Saturday to Wednesday, on Thursday 0730AM - 1230PM)
3. Add holidays of my own for whole year and make it my defaul
calendar for Ms Project.
2. How i export this calendar to other collegues Ms Project.


Thanks and Regar
 