Consider the following scenario:
I am a flooring contractor and I track all my jobs as one MS project.
I am planning work for 2 homes where home 1 (H1) is 1000 sq feet, an
home 2 (h2)is 2000 sq feet.
It takes one person-day to finish 500 sq feet. When I create a new tas
for H1, I simply want to enter 1000 sq ft as an input about H1 and the
I want MS project to calculate 1000/500 = 2 days as the duration for H1
Similarly, I want to enter 2000 sq ft an input about H2 and then I wan
MS project to calculate 2000/500=4 days as the duration for H2.
I know how to create a custom field. This would the area (square feet
of a home, say, homeArea. What I do not know is how make MS Project se
the duration field automatically = homeArea/500
Please help
I am a flooring contractor and I track all my jobs as one MS project.
I am planning work for 2 homes where home 1 (H1) is 1000 sq feet, an
home 2 (h2)is 2000 sq feet.
It takes one person-day to finish 500 sq feet. When I create a new tas
for H1, I simply want to enter 1000 sq ft as an input about H1 and the
I want MS project to calculate 1000/500 = 2 days as the duration for H1
Similarly, I want to enter 2000 sq ft an input about H2 and then I wan
MS project to calculate 2000/500=4 days as the duration for H2.
I know how to create a custom field. This would the area (square feet
of a home, say, homeArea. What I do not know is how make MS Project se
the duration field automatically = homeArea/500
Please help