M
Mike R.
MS Office Project Professional 2003
We're looking to show the resource cost for each resource for each level 2
task.
For Example
Task 2.2 is "Complete PROJECT PROCESS DECISION AND INITIATION SOP" and I'm
trying to display each resource used in Task 2.2 and then the cost associated
with each of those resources.
Will Project 2003 even do this?
We're looking to show the resource cost for each resource for each level 2
task.
For Example
Task 2.2 is "Complete PROJECT PROCESS DECISION AND INITIATION SOP" and I'm
trying to display each resource used in Task 2.2 and then the cost associated
with each of those resources.
Will Project 2003 even do this?