M
Mohammad
In our application (Oracle Database) we want to have
Import/Export capability From/To MS Project. We import
from MS Project via ODBC driver and it imports 21 tables
of MS Project and their related data; it works fine and we
don’t have any issues in this step.
But we want to act vice versa; that means we want to
import to MS Project from oracle application via the ODBC
driver; we insert needed data in the related tables (21
tables of MS Project) by application (Manually); it works
fine when don’t have exception day as a non-working day,
but when we have a exception day (added in the MSP
Calendars and MSP Calendar data); it doesn’t work as well
as before. It brings wrong data. Now I want to know what’s
a calculation formula in the MS Project’s tables and its
related columns such as MSP_TASKS table and
(TASK_START_DATE, TASK_FINISH_DATE, TASK_ACT_START,
TASK_ACT_FINISH, and so on) columns, or what should I do
to fix this issue?
Please help me! Thanks a lot!
Import/Export capability From/To MS Project. We import
from MS Project via ODBC driver and it imports 21 tables
of MS Project and their related data; it works fine and we
don’t have any issues in this step.
But we want to act vice versa; that means we want to
import to MS Project from oracle application via the ODBC
driver; we insert needed data in the related tables (21
tables of MS Project) by application (Manually); it works
fine when don’t have exception day as a non-working day,
but when we have a exception day (added in the MSP
Calendars and MSP Calendar data); it doesn’t work as well
as before. It brings wrong data. Now I want to know what’s
a calculation formula in the MS Project’s tables and its
related columns such as MSP_TASKS table and
(TASK_START_DATE, TASK_FINISH_DATE, TASK_ACT_START,
TASK_ACT_FINISH, and so on) columns, or what should I do
to fix this issue?
Please help me! Thanks a lot!