K
King Kong
Hi all,
I am running into a severe problem with MS-Project.
Here is what I have:
- One pool of ressources (30%, 50%, 80% etc. The wilder you guess the
closer you are to my reality)
- 3 projects I have to deal with with these ressources. The projects
are in different phases of the projects. One is in inception, the
other is in realisation and the last in transition.
- We have to use RUP (Rational Unified Process)
For those who don't know: RUP uses iterations and each iterations
usually has its own individual project plan
How can I use MS-Project best to cover this situation?
I made one calendar in a master project plan.
So far so good. But I need this for the other projects too.
But a simple copy is insufficient because then I would use the
ressources double. I also cannot say the ressources are split 33%,
33%, 33%.
20, 40, 40 si more likely.
And then I have the iterations. So far, for the first project, we used
separate project plans per iteration. Easy. I then manually copied the
basics into the master project plan for the management.
But now, with three projects, smae ressources etc., I have no idea how
to do this best without redudancy or three times work.
Ayn help?
For example:
Is there a way to reference from a master project plan to external
other project plans? So the master is automatically generated?
Or a way that changing ressources in on plan makes the adequate
changes in the other?
Thanks
kay
I am running into a severe problem with MS-Project.
Here is what I have:
- One pool of ressources (30%, 50%, 80% etc. The wilder you guess the
closer you are to my reality)
- 3 projects I have to deal with with these ressources. The projects
are in different phases of the projects. One is in inception, the
other is in realisation and the last in transition.
- We have to use RUP (Rational Unified Process)
For those who don't know: RUP uses iterations and each iterations
usually has its own individual project plan
How can I use MS-Project best to cover this situation?
I made one calendar in a master project plan.
So far so good. But I need this for the other projects too.
But a simple copy is insufficient because then I would use the
ressources double. I also cannot say the ressources are split 33%,
33%, 33%.
20, 40, 40 si more likely.
And then I have the iterations. So far, for the first project, we used
separate project plans per iteration. Easy. I then manually copied the
basics into the master project plan for the management.
But now, with three projects, smae ressources etc., I have no idea how
to do this best without redudancy or three times work.
Ayn help?
For example:
Is there a way to reference from a master project plan to external
other project plans? So the master is automatically generated?
Or a way that changing ressources in on plan makes the adequate
changes in the other?
Thanks
kay