J
j00cy
Hi guys i have a gannt chart, i have one task that goes over 2 days
one task per day) it starts on the 30/11/08, and finishes on th
1/12/08.
i have the first task for 30/11/08 , the date is 30/11/08 on the task
then when i want to put in 1/12/08, it has the start date as th
1/12/08 and finishes on the 2/12/08.
I tried a must finish on contraint but it still comes up as finishin
on the 2nd.
What should i try?
cheer
one task per day) it starts on the 30/11/08, and finishes on th
1/12/08.
i have the first task for 30/11/08 , the date is 30/11/08 on the task
then when i want to put in 1/12/08, it has the start date as th
1/12/08 and finishes on the 2/12/08.
I tried a must finish on contraint but it still comes up as finishin
on the 2nd.
What should i try?
cheer