Z
Ziv
Hello,
I am new to MS Project, I need to allocate a work resource with max-units
calculated per week, e.g. a person which is available for 10 hrs per week. My
problem is that I don't want to limit the resource to an equal distribution
along the week, i.e. it is possible for him to work all his 10 hrs in the
same day of the week, as long as he won't work on any other day at that week.
Currently it seems that when I set Max Unit of this resource to 25% , which
based on the standard calendar of 40 hrs per week, is 10 hrs per week, MS
project automatically distributes these 10 hrs along the week, i.e. 2 hrs per
day, and will warn for over-allocation if this person works more then 2
hours, which is not what I wanted. Can you help me with this?
Thank you!
Ziv
I am new to MS Project, I need to allocate a work resource with max-units
calculated per week, e.g. a person which is available for 10 hrs per week. My
problem is that I don't want to limit the resource to an equal distribution
along the week, i.e. it is possible for him to work all his 10 hrs in the
same day of the week, as long as he won't work on any other day at that week.
Currently it seems that when I set Max Unit of this resource to 25% , which
based on the standard calendar of 40 hrs per week, is 10 hrs per week, MS
project automatically distributes these 10 hrs along the week, i.e. 2 hrs per
day, and will warn for over-allocation if this person works more then 2
hours, which is not what I wanted. Can you help me with this?
Thank you!
Ziv