B
Barry
When I approve time on my project, I am expecting to see the start of the
remaining work prior to the status date (current date) to be moved to be
moved forward to the status date. I am not seeing that happen in my plan. I
do see the start of the remaining work being moved forward to the last date
that the task was updated, even if it is before the status date.
I have the following collaboration calculations set:
Updating task status updates resource status
Move end of completed parts after status date back to status date
And move start of remaining parts back to status date
Move start of remaining parts before status date forward to status date
Also note: status date in project information is not set.
What am I missing?
remaining work prior to the status date (current date) to be moved to be
moved forward to the status date. I am not seeing that happen in my plan. I
do see the start of the remaining work being moved forward to the last date
that the task was updated, even if it is before the status date.
I have the following collaboration calculations set:
Updating task status updates resource status
Move end of completed parts after status date back to status date
And move start of remaining parts back to status date
Move start of remaining parts before status date forward to status date
Also note: status date in project information is not set.
What am I missing?