MS Project Office and PWA

V

Vijay

This is a strange problem i am facing. One of the resources is having this problem. He has entered only 8 hours each in PWA for 2 weeks (80 hours). In project plan it shows that he has enetered 8 hours each for 4 weeks(160 hours). Any idea what might be causing this issue. This is just happning to one user and i am very sure that no one is manually updating Project Plan
 
P

Prasanna Adavi

Are the hours being entered in a timesheet or My tasks page.

Also, did the resource mark the task 100% complete. if it was a 4 week task
and the resource marked 100% complete on it, Project will treat that as
planned hours = actual hours and populate.
 