L
L Kelly
Hi there -
Has anyone ever come across an error in a MS Project
schedule like this one:
I have tons of tasks and resources, etc. Schedule is
baselined and I have been statusing fine for the past few
months.
I want to enter some additional tasks at say task ID line
212. I hit Insert and enter one new task line just fine.
When I tried to enter the next one - it tells me "No
calculations can be completed at this time due to circular
reference". Circular link relates to task 99 (not task ID
212 or even close to that task ID number ) because a
successor is creating the circular link. To solve I am
supposed to click on task 99 and and to unlink
predecessors and successors".
When I look at task ID 99, there is no successor or
predecessor ID listed AT ALL for that task! I even went to
those columns and hit backspace to get rid of anything I
may not be seeing for some reason.
So now because it won't calculate, if I try to link task
ID 213, 214 etc Finish-Start to 212, it shows a link but
the start date is the start date of the project, not
following the end date of 212!
Any help would be MOST appreciated! Is my schedule
corrupted or something?!
THANKS
Has anyone ever come across an error in a MS Project
schedule like this one:
I have tons of tasks and resources, etc. Schedule is
baselined and I have been statusing fine for the past few
months.
I want to enter some additional tasks at say task ID line
212. I hit Insert and enter one new task line just fine.
When I tried to enter the next one - it tells me "No
calculations can be completed at this time due to circular
reference". Circular link relates to task 99 (not task ID
212 or even close to that task ID number ) because a
successor is creating the circular link. To solve I am
supposed to click on task 99 and and to unlink
predecessors and successors".
When I look at task ID 99, there is no successor or
predecessor ID listed AT ALL for that task! I even went to
those columns and hit backspace to get rid of anything I
may not be seeing for some reason.
So now because it won't calculate, if I try to link task
ID 213, 214 etc Finish-Start to 212, it shows a link but
the start date is the start date of the project, not
following the end date of 212!
Any help would be MOST appreciated! Is my schedule
corrupted or something?!
THANKS